Top Project Metrics and Process Metrics in Project Management for 2022-23 | Simplilearn

  1. Schedule Variance: Any difference between the scheduled completion of an activity and the actual completion is known as Schedule Variance.

    Schedule variance = ((Actual calendar days – Planned calendar days) + Start variance)/ Planned calendar days x 100.

  2. Effort Variance: Difference between the planned outlined effort and the effort required to actually undertake the task is called Effort variance.

    Effort variance = (Actual Effort – Planned Effort)/ Planned Effort x 100.

  3. Size Variance: Difference between the estimated size of the project and the actual size of the project (normally in KLOC or FP).

    Size variance = (Actual size – Estimated size)/ Estimated size x 100.

  4. Requirement Stability Index: Provides visibility to the magnitude and impact of requirements changes.

    RSI = 1- ((Number of changed + Number of deleted + Number of added) / Total number of initial requirements) x100.

  5. Productivity (Project): Is a measure of output from a related process for a unit of input.

    Project Productivity = Actual Project Size / Actual effort expended in the project.

  6. Productivity (for test case preparation) = Actual number of test cases/ Actual effort expended in test case preparation.

  7. Productivity (for test case execution) = Actual number of test cases / actual effort expended in testing.
  8. Productivity (defect detection) = Actual number of defects (review + testing) / actual effort spent on (review + testing).

  9. Productivity (defect fixation) = actual no of defects fixed/ actual effort spent on defect fixation.

  10. Schedule variance for a phase: The deviation between planned and actual schedules for the phases within a project.

    Schedule variance for a phase = (Actual Calendar days for a phase – Planned calendar days for a phase + Start variance for a phase)/ (Planned calendar days for a phase) x 100

  11. Effort variance for a phase: The deviation between a planned and actual effort for various phases within the project. 

    Effort variance for a phase = (Actual effort for a phase – a planned effort for a phase)/ (planned effort for a phase) x 100.

    PMP Certification Made More Accessible

    PMP Certification Training

    Explore CoursePMP Certification Made More Accessible